Legal Challenges and Financial Strain Over Ha Belo Electricity Substation Project
The government of Lesotho is facing a complex legal and financial dilemma following the High Court’s decision to nullify its termination of the contract with Phaks Joint Venture (Phaks JV) for the construction of the Ha Belo electricity substation. This ruling has placed the project in limbo, as the government now finds itself bound by two conflicting contracts—one with Phaks JV and another with Actom (Pty) Ltd, a South African company that was contracted to complete the work left unfinished by Phaks JV.
The High Court’s decision came after the Ministry of Energy terminated Phaks JV’s contract, citing its failure to complete the M86.6 million project, which had escalated to M170 million due to alleged inefficiencies. The ministry then engaged Actom at a cost of M49,720,215.42 to take over the remaining works. However, Phaks JV contested the termination, arguing that it remained legally obligated to continue the project.
This dispute led the government to seek court intervention, but the Northern Division of the High Court in Leribe declined jurisdiction, stating that the Ministry should have pursued arbitration first. Justice Makampong Mokhoro ruled that the original contract remains binding, emphasizing the importance of adhering to the Arbitration Act No. 12 of 1980. The court dismissed the government’s application, citing procedural lapses.
Background of the Ha Belo Project
The Ha Belo 33/11kV substation and 33kV line project was awarded to Phaks JV on 18 August 2021, with an 18-month completion timeframe. However, the project has been plagued by allegations of corruption, with millions of maloti reportedly paid to the contractor despite minimal progress. Work began in November 2021 and was initially scheduled for completion by April 2023, but costs ballooned to M121,577,004.21, leading to additional funding.
The project, part of the World Bank-funded Lesotho Renewable Energy and Energy Access Project (LREEAP), aimed to expand electricity access in peri-urban and rural areas. Despite this, the project has faced significant setbacks, including a M22 million refund to the World Bank in June 2025 due to mismanagement of funds.
Corruption Allegations and Leadership Changes
Corruption allegations have surrounded the project from the start. The Ministry of Energy’s Principal Secretary, Tankiso Phapano, has distanced himself from the scandal, noting that he assumed office in January 2024, long after the contract was signed. His predecessor, Themba Sopeng, was charged in January 2025 with corruption, embezzlement, and money laundering related to the project. Sopeng was accused of facilitating the tender award to Phaks JV without proper procurement procedures.
In response to the project’s challenges, Prime Minister Sam Matekane announced in March 2025 that an additional M50 million would be required to complete the project. The government then contracted Actom (Pty) Ltd, which had previously been a subcontractor to Phaks JV, to take over the remaining works.
Government’s Response and Future Outlook
According to a contract seen by the Lesotho Times, the Ministry of Energy entered into a M49,720,215.42 agreement with Actom on 20 September 2025. In a statement, the ministry blamed the project’s cost overruns on poor administration and mismanagement, noting that the contractor was paid for equipment that was never delivered. The ministry claimed that it had to pay for the equipment to prevent it from being auctioned, allowing Actom to take over the remaining work.
It remains unclear whether the government will appeal the High Court’s ruling or pursue arbitration. If the court’s decision stands, it could further highlight the government’s struggles with legal processes. Just last week, the government dissolved the Government Asset Search and Recovery Task Team (GASRTT), despite its three-year operation.