False Claims of $75m Investment

Posted on

Legal Requirements for Mining Operations in Ghana

Under the Minerals and Mining Act, 2006 (Act 703), any company or individual planning to conduct mining activities must fulfill several legal requirements. One of the most critical is obtaining the necessary permits from the Environmental Protection Agency (EPA) and the Mineral Commission. These permits are essential to ensure that mining operations comply with environmental and safety regulations.

According to Section 18 of the Minerals and Mining Act 2006 (Act 703), read in conjunction with the Environmental Assessment Regulations, L.I.1652 of 1999, the holder of a mineral right must obtain approvals and permits from the Forestry Commission and the Environmental Protection Agency. This is to protect natural resources, public health, and the environment. Additionally, the holder must comply with all regulations made under the Act and other relevant enactments for environmental protection during the exploitation of minerals.

Section 2 of the Act 703, specifically Regulation 2 under L.I.2182, states that a person shall not engage in mining or processing of minerals without obtaining an Operating Permit from the Chief Inspector of Mines. This operating permit serves as the final authorization before mining can commence, following all other required approvals such as the EPA permit and mining lease.

Current Situation at the Bogoso/Prestea Mine Site

Heath Goldfields has been accused of violating these legal requirements by proceeding with mining activities without the necessary permits. The company has reportedly started re-mining materials from the old tailings dam and hauling material from the pre-strip pit opposite the Bondaye Shaft, which could lead to further underground flooding. They have also begun mining the old tailings dam despite the conditions set by the Mines Inspectors requiring the dam to be raised or a new Tailings Storage Facility (TSF) to be built first.

The current state of the mine shows significant challenges. The underground areas at 17level and 24level are still flooded, with water levels 108ft below 18level as of 20/10/2025. Key installations and equipment in these areas remain inaccessible. On the surface, some parts of the BIOS plant have been cannibalized to repair the CIL plant, but the overall condition of the plant requires major overhauling.

Financial and Operational Mismanagement

Heath Goldfields has claimed to have invested USD75 million in preparatory and infrastructure works, but this claim is being questioned. The processing plant has only seen minor repairs, with components being reconditioned rather than replaced. Major parts needed for the plant were not available on time, and the company faced a stop work notice from the Minister on 5th July 2025. The focus seems to be on getting the plant operational within the 120-day deadline, even if it means bypassing key systems.

On the TSF uplift, the engineer of records, Knight Piesold, has not been paid and is not on site. The embankment rise is on hold, and equipment clearing the footprint of the embankment is limited. At Prestea Underground (PUG), the working areas at 17level and 24level remain inaccessible due to flooding, raising questions about where the claimed USD75 million was spent.

Worker Payments and Company Obligations

Regarding worker payments, Heath Goldfields has only settled 8 months of salary arrears, totaling about USD7 million, for the period from February to September 2024. However, many other entitlements, including severance packages, SNNIT contributions, and end-of-contract benefits, remain unpaid. The company has also failed to make any payments to SNNIT, despite claiming to have done so.

Additionally, there are concerns about the ownership structure of Heath Goldfields. While the Managing Director claims the company is 90% Ghanaian-owned, the source of the remaining 10% and the funding for the USD75 million investment remain unclear. Investigations into potential money laundering and the legitimacy of the funds are warranted.

Conclusion

The situation at the Bogoso/Prestea Mine highlights serious legal and operational violations. Heath Goldfields appears to be using PR strategies to mislead the community while failing to address the real issues affecting the mine. The lack of proper permits, ongoing flooding, and unresolved financial obligations indicate a deep-rooted problem that needs urgent attention. The Bogoso/Prestea community should remain vigilant and demand transparency from the company and relevant authorities.