The Impact of the Port Harcourt Refinery Shutdown
The shutdown of the Port Harcourt Refinery, Nigeria’s largest refinery, has cost the government over $249.7 million, equivalent to N366.210 billion, over a five-month period from May 24, 2025, to October 31, 2025. This loss was revealed by Daily Trust, which analyzed the financial implications of the shutdown.
The refinery, located in Eleme, Rivers State, was reopened in November 2024 and began operations. According to the Nigerian National Petroleum Company Limited (NNPCL), the revived facility had a production capacity of 60,000 barrels per day and produced at least 1.4 million liters of Premium Motor Spirit (PMS) daily. It also produced 900,000 liters of kerosene, 1.5 million liters of Automotive Gas Oil (Diesel), 2.1 million liters of Low Pour Fuel Oil (LPFO), and additional volumes of Liquefied Petroleum Gas (LPG).
The Federal Government had approved $1.5 billion in 2021 for the comprehensive rehabilitation of the refinery before it was reopened under Mele Kyari’s leadership on November 26, 2024. However, the refinery was shut down again on May 24, 2025, for planned maintenance and a sustainability assessment, just six months after its previous operational resumption.
Financial Losses Due to the Shutdown
The financial losses incurred due to the shutdown are staggering. With the landing cost of PMS at N900 per liter, the daily loss amounts to N1,260,000,000, totaling N196.560 billion over 156 days. Similarly, the price of kerosene at N1,005 per liter results in a daily loss of N904,500,000, or N141,102,000,000 over the same period. For diesel, priced at N1,220 per liter, the daily loss is N1,830,000,000, leading to a total of N285,480,000,000 over 156 days.
These figures bring the total losses caused by the shutdown to N366.210 billion, equivalent to $249.7 million over five months and six days.
Reasons Behind the Shutdown
According to NNPCL, the shutdown was necessary for planned maintenance and a sustainability assessment. However, the company had previously reported that it was losing between N300 million and N500 million monthly operating the Port Harcourt refinery before suspending rehabilitation works at the facility.
Some staff members, who spoke with Daily Trust on condition of anonymity, claimed that the refinery did not produce as claimed, suggesting that products were brought in from other sources to be sold to marketers. A staff member identified as Teska said that management banned any staff from speaking to the press, adding that neither the new nor old plant was working at the time of the shutdown.
Daily Trust observed that the refinery had 506 staff members as of July 2025, two months after the shutdown.
Staff Perspectives and Challenges
Several staff members told Daily Trust that the refinery did not produce anything during the period from November 2024 to May 2025. They alleged that refined products were brought in from Indorama Petrochemicals and then loaded through the NNPC refinery. One staff member said, “They were not refining here, to the extent that they warned the workers never to talk to the press.”
About five staff members who spoke with Daily Trust around the refinery host community said they were not aware if production was going on between November 2024 and May 2025. They added that they had seen marketers loading from the refinery, but how it was refined was unclear to them.
Challenges Facing Public Refineries
The National Association of Plants Operators (NAPO) stated that competition from private refineries in Nigeria and outside the country is a major challenge for public refineries. NAPO’s National President, Mr. Harold Benstowe, suggested that if the refinery were managed by capable companies, it would function properly.
He explained that the monopoly in fuel production in Nigeria is a key factor preventing public refineries from functioning effectively. He added that some oil magnates benefit from the refinery’s failure, as they import refined products from abroad and sell them back to Nigerians.
Calls for Reform and Accountability
The Independent Petroleum Marketers Association of Nigeria (IPMAN) urged the NNPC Group Chief Executive Officer (GCEO), Bayo Ojulari, to either fix the refinery immediately or resign. IPMAN’s Eastern Zonal Secretary, Comrade Emmanuel Inimgba, expressed concerns over the delayed rehabilitation of the refinery, which he believes is being handled unprofessionally.
Inimgba noted that the refinery’s shutdown has resulted in thousands of job losses, affecting various stakeholders. He emphasized that fixing the refinery would create jobs, boost the local economy, and improve fuel supply and distribution.
Expert Insights on the Implications
Wumi Iledare, a Professor Emeritus of Petroleum Economics, highlighted the dual financial impact of the refinery’s shutdown: lost foreign exchange from fuel imports and lost domestic value creation. He explained that while temporary shutdowns may be necessary, inefficient operations can erode value faster than well-managed maintenance.
Iledare stressed the need for depoliticized management, transparent crude supply agreements, and performance-based operations to make public refineries successful.
Conclusion
The shutdown of the Port Harcourt Refinery has had far-reaching economic consequences for Nigeria. From financial losses to job cuts and supply chain disruptions, the situation highlights the urgent need for reform and accountability in the management of public refineries. As stakeholders continue to push for solutions, the path forward requires a combination of transparency, efficiency, and commercial discipline to ensure the long-term viability of Nigeria’s energy sector.