LNG Project Launch: What Lies Ahead Post Host Government Agreement Signing

Posted on

The Path to Implementation: Understanding the Steps After HGA Signing

A few months ago, there was news that the signing of the long-awaited Host Government Agreement (HGA) between international oil companies and the Government of Tanzania was imminent. This development marks a significant milestone in the journey of the project. However, it is just the beginning. For the people of Tanzania and stakeholders interested in the opportunities this project presents, understanding what comes next is essential.

The next major step after the HGA signing is the Final Investment Decision (FID). This decision will determine whether the project remains viable from both economic and technical perspectives. It also considers the global shift towards renewable energy sources like solar and wind, which may influence the project’s future.

To move forward with an LNG project, several critical activities must be undertaken. These include technical assessments, commercial evaluations, and financial analyses. Let’s explore each of these in detail.

Technical Assessments

Technical assessments are crucial for defining the project’s technical aspects and selecting contractors for engineering, procurement, and construction (EPC) works. Key steps in this process include:

  • Pre-Front End Engineering Design (Pre-FEED): This involves preliminary designs led by contractors, informed by initial estimates of gas reserves, exploitation potential, liquefaction sites, and pipeline routes.
  • Front End Engineering Design (FEED): Following Pre-FEED, FEED focuses on optimizing plant equipment and configurations. This phase provides a clearer scope for EPC contract bidders.
  • EPC Contract and Bidding Process Structuring: Proper structuring of the EPC contract is vital to avoid implementation issues. Key considerations include:
  • Incorporating the project structure into the contract in a clear and enforceable manner.
  • Ensuring the contract is effective for successful management, especially with potential changes during its life.
  • Implementing sufficient protections for both investors and bidders.

Commercial Assessment

The commercial assessment involves securing necessary project agreements and LNG offtake contracts. Important agreements include:

  • Domestic Gas Sales Agreement (GSA): Covers gas sold in the local market.
  • LNG Sale and Purchase Agreement (SPA): A critical component linking the liquefaction plant to the receiving terminal. There is no universal model for SPA, with most parties using their preferred forms.
  • Other Agreements: Includes project enabling agreements, shareholders agreements, and liquefaction agreements.

Financial Assessment

The financial assessment relies on the technical and commercial feasibility of the project to secure capital investments. Key activities in this workstream are:

  • Developing a Financial Model: A comprehensive model captures inputs from technical and commercial workstreams. It typically covers 30 to 40 years of gas exploitation and includes sensitivity analyses to assess different scenarios.
  • Assessing Bankability: Evaluates the project’s ability to repay debt on schedule. Criteria include offtake assurance, revenue stability, and shareholder guarantees.
  • Securing Financing Commitments: Involves obtaining commitments from various financiers, including development institutions and government bodies. Instruments used in blended finance include:
  • Grant and Technical Assistance: Supports investors/sponsors pre-or post-investment.
  • Guarantees: From agencies like IFC to reduce risk for other investors.
  • First Loss Guarantee: A development finance institution takes the first loss if the project underperforms.
  • Concessional Debt: Offers lower returns or extended repayment periods compared to private investors.

Final Investment Decision (FID)

The FID is the final commitment to proceed with the project. It requires completion of government agreements, such as land allocation and access, and securing financing from various providers, including export credit agencies, multilateral banks, and commercial lenders.

While much remains to be done before gas revenues can be realized, the HGA is a critical first step. Accelerating subsequent activities is essential to ensure that Tanzania and its people can benefit from the country’s gas resources before the global energy transition reduces the demand for fossil fuels.

Chacha Winani is an Associate Director, Deals — Transaction Advisory, PwC Tanzania, and a Certified Public-Private Partnership Professional (CP³P). The views expressed do not necessarily represent those of PwC.